Prestwick Common Revitalization Project

Keeping You Updated

Updated: September 5, 2017

Prestwick Common work is progressing along at a quick pace.  With two different contractors on site, one for the waterpark and the other doing the building, work is now proceeding with changes happening daily.

The contractor on the building has been doing the rough-in for electrical and plumbing now that the walls have been installed.  They were waiting on inspections for this work earlier in the week.  The framers will be on site and the plan is to have the roof completed by Friday, which will allow for the closing in of the building to allow the other trades to start their work.  The complex plumbing for the splash park requires a lot of detailed work to be undertaken in the mechanical room.  Once the floor has been poured, the pumping systems for the splash park will be able to be installed.

 The splash park contractor is currently finishing up their sub surface work on the splash pad which is just north of the fountain.  The surface and plumbing preparation for this piece of the project requires good weather, and fortunately we are getting that to support the pouring and finishing of the concrete which will start September 18.  Shortly after, you will then get to see the Waterplay structures installed to get an appreciation of some of the above ground water features provided for the park.  There are also many ground level spray features.  The pouring of concrete will also occur for the fountain in the same time frame.

You may have noticed that the signs we had around the park have come down.  That was due to vandalism that occurred over the long weekend.  We will not be putting them back up, so we encourage our members to keep visiting this page to keep up to date with the progress of the project.



Updated: September 5, 2017

Prestwick Common has made immense steps towards completion but unfortunately there is some more work left to do and it will not be completed by the end of the summer. We are looking to have it complete by mid- October 2017, with exciting new features for all seasons and for the entire family to enjoy. Stay tuned for more construction updates by visiting our website.

Thank you for your continued patience.

.  

Updated: August 25, 2017

Significant progress has been made on the Prestwick Common Revitilization project in the past few days.  Thanks go out to the residents of Prestwick Boulevard who have lived with the inconvenience of a parking ban and the remainder of Prestwick residents who endured some inconvenience on their drive into work and home on Thursday August 24.  Today we have completed the installation of the walls of the pre-cast building.  The road closure and parking ban was necessary in order to lift these extremely heavy panels into place.

Over the past couple of months, a lot of work that has gone on has been below the surface, and not really noticeable unless you walked over to the fence and looked into the site.  The progress of the project is moving along quite quickly with the underground work being mostly completed for the fountain, deep storage tank and the building.  In the coming days the sub-surface work will occur for the splash pad.

 In order to save costs, our very own McKenzie Towne landscaping team is prepping the area around the hill for the planting of shrubs and grass. 

With the walls for the building now installed, next week you will see the roof go on and be able to appreciate the effort that has gone into the design to ensure that the building fits in with the park.  You may notice that the look of the stone pillars are replicated in the wall panels for the building.  Next week, you may notice the beautiful wood beams installed that form part of the canopy extending on the west side of the building.

Although the area around the fountain has currently a large excavation, which is necessary to install the natural gas lines for the fire pits and the multiple water jets, work will be completed soon so that you can have an idea of what this will look like.  The fountain is and will be a focal point of the revitalization.

 So, again thanks to everyone for their patience as we work to improve and revitalize Prestwick Common.

 

 

Updated: July 23, 2017

The Prestwick Common Revitilization project continues to move ahead.  With some weather related delays and others associated with engineering permits, resident’s will now start to see significant visible changes on the site occur in the next few weeks.  We have completed the construction of the retaining walls, which now allows for the excavation of the footprint of the splash park.  The toboggan hill needed to be cut back in order for the splash park to fit between the playground and the fountain.  In the coming weeks, significant underground work will be undertaken to allow the installation of water and sewer lines as well as the holding tank for the splash park system.  Once this work is completed, the installation of the mechanical building and washrooms will occur in late August.  We anticipate having a confirmed date for completion calculated in the first few weeks of August.  Although we have had a hot summer, a significant downpour affects all of the deep excavation work that we are currently undertaking on the site and requires us to stop and allow things to dry up.  Once this underground work is done, weather will not be as big of a factor, until we start to pour concrete.  Stay tuned for our next update.



Updated: July 16, 2017

Construction update:

There were minor delays due to the rain but the site was dry enough to complete work on the final wall and its reinforcements, wall excavations, and new walls were poured as well as the complete dismantle of the previous wall.

The construction team also removed eighteen tandem loads of excavated material removed from the site.



Updated: July 4, 2017

We have a construction update: 

All the final reinforcement and verification, retaining wall footings is poured and old footing removed, retaining wall rebar is cut and installed and reinforcement wailers are constructed and completed. The retaining wall forming is cut to size and is 80% complete. Other retaining wall construction is at 50% complete. And site wide clean up, house-keeping, and fence lines are secured and all fully completed. 

 

Updated: June 20, 2017

McKenzie Towne Council has successfully applied for and received $125,000 in additional grant funding through the Government of Alberta's Community Facility Enhancement Program.

The Council's application proposed to rehabilitate and renovate Prestwick Common which includes upgrades to the fountain and seasonal amenities such as the splash park for the summer and an ice rink with fire pits for the winter months. The Council plans to build washrooms onsite - it is an important addition for the residents of McKenzie Towne. These will be open year-round and maintained and locked nightly by Council staff.

We would like to extend our gratitude to the Honourable Ricardo Miranda, Minister of Culture and Tourism, Honourable Premier Rachel Notley, MLA Ric McIver and the Alberta Government for making improvements and upgrades to our community possible.

Read about the Grant Approval Letter here.

 

Updated: June 14, 2017

We are happy to share an update on the construction of Prestwick Common. We experienced some delays from the City of Calgary, but we were able to meet their requirements and have been given the permissions to resume construction. As of today, all the demolition work, removal of the old building, excavation and tree protection has been completed. We have the same desire for the park to be open and enjoyed by all, so we will do everything we can to get this completed as soon as possible.

We thank you for your continued support and patience. Don’t hesitate to ask any questions you may have about the project. We will keep you posted on any further updates.

Thank you.

 

Updated: May 25, 2017

A couple pictures of the current state of the construction process.

 

More Progress!

Updated: May 11, 2017

The old fountain has been removed and the new one will be put in with the new splash park equipment.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Demolition is completed
Updated: April 26, 2017

Demolition of the existing building has been completed; work on site will continue as permitted. Thank you for your patience and understanding.


 

 

Fencing at Prestwick Common
Updated: March 15, 2017

Installation of construction fencing around the entire Prestwick Common park site will begin as of Thursday, March 16th. The City of Calgary has mandated that for safety and security reasons the fencing will remain onsite until the project is completed, meaning that the park will be closed to the public during this time.

Construction will begin the week of March 20th, 2017.


Letter of Greeting
Updated: February 24, 2017

Although the Honourable Navdeep Bain, Minister of Innovation, Science and Economic Development could not attend McKenzie Towne Council's ground breaking ceremony, Western Economic Development Canada (WD) shared this letter of greeting in support of the project. McKenzie Towne Council received funding for the project through WD's Canada 150 Community Infrastructure Program.

 


Groundbreaking ceremony kicks off construction announcement
Updated: February 21, 2017

On Saturday, February 18, 2017 McKenzie Towne Council hosted a groundbreaking ceremony and community event at Prestwick Common to kick off the much anticipated construction of the Prestwick Common Revitalization Project. The ceremony was lead by Rob Van Gastel, President of McKenzie Towne Council. Joining him with words of support were Stephanie Kusie - past President of the McKenzie Towne Community Association, Rick McIver - MLA for Calgary Hays, and Shane Keating - Councillor for Ward 12. Also in attendance were members of McKenzie Towne Council's Board of Directors and many excited residents and families.

The event featured skating, music and hot dogs. Coffee and hot chocolate was kindly donated by McKenzie Towne Tim Horton's.

Construction will begin in early March. Fencing will be placed around the entire park area of Prestwick Common. The Project is planned to be completed and open for July 1, 2017 on Canada Day for a grand opening celebration.



Photo: Left to right - Rob Van Gastel President - McKenzie Towne Council, Shane Keating - Councillor for Ward 12, Rick McIver - MLA for Calgary Hays, and Stephanie Kusie - past president of the McKenzie Towne Community Association.


Frequently Asked Questions
Updated: February 13, 2017

clientuploads/_photos/Picture2.pngWhat is the Prestwick Common Revitalization Project?

Due to aging infrastructure and its imminent replacement, coupled with the opportunity to apply for a Federal development grant, the decision has been made to revitalize the Prestwick Common amenity. The goal is to install splash park spray structures, create a more level winter skating surface and build onsite washrooms. And, along with funding from the Federal Government, transform Prestwick Common into a multi-generational landmark amenity that commemorates the 150 anniversary of the Confederation of Canada and McKenzie Towne Council's 20th anniversary (1995 - 2015). Please read previous posts below to learn more about the project.

When will construction begin and end?

The anticipated beginning of construction will be March 2017. The anticipated opening date will be July 1, 2017, to celebrate Canada Day.

What is the name of the new park?

“Anniversary Park”. The name was arrived at because the park will be commemorating Canada’s 150th, as well as McKenzie Towne Council’s 20th anniversaries!

How much will the project cost?

The approximate cost is $1.7 million.

Will Annual Fees go up due to this project?

No. Annual Fees will not increase because of this project and its costs.

What is the grant funding from the Canada 150 Community Infrastructure Program (CCIP)?

The CCIP is part of Canada 150 Celebrates, the Government of Canada's celebration of our country's 150th anniversary. Through investments in community infrastructure, the Government of Canada will invest in projects that celebrate our shared heritage, create jobs, and improve the quality of life for Canadians.

Under the theme Giving back to Canada: shaping the future, leaving a lasting legacy and giving a gift to Canada, the CCIP will invest $150 million over two years to support projects that rehabilitate existing community facilities across Canada. These projects will ensure a lasting legacy as a result of Canada 150 and strengthen communities from coast to coast to coast.

Western Economic Diversification Canada (WD), on behalf of the Government of Canada, will deliver the CCIP in Western Canada. WD will invest in projects that rehabilitate or improve cultural and community infrastructure, which will help communities realize long-term growth and vibrancy in the years to come.

Source: http://www.wd-deo.gc.ca/eng/18872.asp

What age groups will the revitalized park serve?

Ages 1 – 99.

Why can’t the park be fenced?

The Common cannot be fenced for two reasons:

  1. To receive this grant funding, our amenity must meet the follow criteria (and more under Eligible Activities):
    a.
    Be for the rehabilitation, renovation, or expansion of existing infrastructure for public use or benefit;
    b.
    Be community-oriented, non-commercial in nature and open for use to the public and not limited to a private membership;

  2. The City of Calgary owns the land that Prestwick Common is situated on and is zoned for public use. McKenzie Towne Council only owns the physical structures in the park.

Development Permit Conditionally Approved
Updated: January 18, 2017

Another step closer to breaking ground! McKenzie Towne Council's Development Permit was conditionally approved by the City of Calgary. MTC is working to establish a construction timeline and have it publicly as soon as possible.


Development Permit Drawings received by MTC
Updated: November 23, 2016

McKenzie Towne Council is excited to present our Development Permit Drawings for the Prestwick Common Project. Currently, the drawings are in the circulation stage among City business units and the McKenzie Towne Community Association. MTC aims to break ground in February 2017, complete construction in June 2017 and host a grand opening on Canada Day, July 1, 2017.

Click here to view the drawings.


 Town Hall meeting results & project next steps
Updated: February 1, 2016

McKenzie Towne Council hosted two open houses and had very low attendance. Attendees expressed minimal opinions regarding plans to revitalize Prestwick Common. However, the greatest concern that was brought to our attention was parking availability around the Common.

Next steps: The Board of Directors has approved to proceed to develop an architectural plan for the potential splash park area that would incorporate an upgraded fountain feature, improved fire pit - followed by an RFP process for a building that will house mechanical and chemical rooms, washrooms and a multi-use space.


Town Hall Meeting Dates & Submit Feedback
Updated: November 20, 2015

Submit Project Feedback

Leading up to the Town Hall meetings regarding Anniversary Park at Prestwick Common, McKenzie Towne Council welcomes your feedback and thoughts about the project. Please read all of the posts below before submitting your feedback. Your submissions well help MTC with keep resident interests in mind and providing appropriate information about the project to keep everyone on the same page.

Prestwick Common Revitalization Project Feedback Form

First and Last Name
Feedback

Town Hall Meetings

McKenzie Towne Council's Prestwick Common Committee will be hosting to Town Hall meetings at McKenzie Towne Hall in December. All McKenzie Towne Residents are invited to attend to share their thoughts and ideas, as well as to learn about plans and progress and have questions answered. These meeting will be an open discussion forum to maintain awareness from both Board member and resident perspectives.

Meeting dates:

Sunday, December 13th from 3:00 p.m. - 5:00 p.m.

Monday, December 14th from 6:30 p.m. - 8:30 p.m.

Download the Prestwick Common Project Feedback Brochure


An Overview on the Prestwick Common Revitalization Project

Updated: October 8, 2015

Brookfield Developers built McKenzie Towne as an open and publicly accessible community. Whereas developers of other communities with resident associations built fenced-in amenities, enabling controlled access. This makes McKenzie Towne unique in that residents can enjoy the community’s amenities without limitation to their friends and families, and allows all Calgarians to visit and enjoy this wonderful community, too.

Prestwick Common was due – based on its amenity life cycle analysis – for redevelopment in 3-5 years from now. It is currently an aesthetically pleasing fountain used as a splash park in the summer, and a skating rink with fire pit in the winter.

Upon discovery of the Government of Canada’s Canada 150 Community Infrastructure Program, McKenzie Towne Council (MTC) saw an opportunity to revitalize the Common, turn it into a landmark destination and save on redevelopment costs. The revitalized landmark will celebrate and commemorate the 150th anniversary of Canada’s Confederation in 2017 for future generations of the community.

The approved federal funding allows MTC to proceed with redevelopment fountain/splash park sooner than projected. McKenzie Towne Council must still contribute money (alongside federal funding) to revitalize the publicly used amenity, owned by MTC, on City of Calgary property.

McKenzie Towne Council identified two areas of improvement with the Prestwick Common revitalization project:

1. Converting the fountain area into a more age appropriate and interactive splash park, as well as an easier to flood ice surface in the winter. The fountain/fire pit will remain as a feature in Prestwick Common.

2. The addition of washrooms – we receive constant feedback from users that washrooms would drastically improve enjoyment of the site, while adding some much needed convenience.

The Board and staff of MTC have been fiscally responsible for over a decade and Annual Fees will not increase because of this new project. In fact, McKenzie Towne Council is now debt free, twelve years ahead of schedule! Annual Fees go towards recreation programming and event support at the Towne Hall, year-round maintenance of 14 amenities, enhanced grounds keeping throughout the community and much more.

McKenzie Towne Council is proud to have the ability to take on this project, for the benefit of McKenzie Towne’s residents, in a fiscally responsible manor while improving a major amenity that will have a long lasting and historical imprint within the community.

McKenzie Towne Council welcomes feedback. Email inquiries@mtcouncil.com.


Announcement: Funding for the Prestwick Common Revitalization Project

September 2, 2015

McKenzie Towne Council has successfully applied for and received $215,000 in grant funding through the Government of Canada's - Canada 150 Community Infrastructure Program.

The Council's application proposed to rehabilitate and renovate the existing the fountain area of Prestwick Common into a family friendly splash park area with features for toddlers to teens. The project will also keep the ability to turn the Common into a pleasure rink in the winter, with a new and better graded surface that will be easier to flood and maintain ice. Additionally, Council plans to build washrooms onsite - it is important to the residents of McKenzie Towne, as well as all users of the Common.

Council is excited to be able to pursue a project that will benefit the community's residents and improve a site that has long needed some additional amenities and revitalization. While many of the project details need to be worked out, it is scheduled to begin in the spring of 2016 and be completed by the fall of 2017.

The announcement of approved funding was made on July 30th by Michelle Rempel, Minister of State for Western Economic Diversification and Member of Parliament for Calgary Centre - North. $1.8 million was announced for 17 projects benefiting Calgary under the Canada 150 Community Infrastructure Program.

"The 150th anniversary of Confederation is a great opportunity to celebrate Canada's rich history and heritage, and to look forward to its promising future. By supporting community associations across the West through the Canada 150 Infrastructure Program, we are helping all Canadians celebrate this important milestone while leaving a lasting legacy of improved local infrastructure." - The Honourable Michelle Rempel, Minister of State for Western Economic Diversification and Member of Parliament for Calgary Centre - North.

 

McKenzie Towne residents that wish to be involved in the project are welcome to email the President of McKenzie Towne Council: president@mtcouncil.com